As of September 16, 2021, 12 wind power poles at AMACCAO Quang Tri 1 wind power project have been installed. Currently, the project is in the process of completing electricity, expected to be put into operation on September 30.
Vinadic ME is the unit conducting M&E construction at the AMACCAO Quang Tri 1 Wind Power project.
This is a project with a large investment scale and high technical requirements in the stages of installation and construction. Therefore, the construction units must also be professional units, have good technical expertise, and have construction experience in large projects.
AMACCAO Quang Tri 1 Wind Power Project is one of the top 15 energy investment projects in Quang Tri, invested by AMACCAO. The project started construction in early July and is expected to be completed by the end of September.